Energy Audit

  • June 11, 2016
Project Description

Government Facilities
Years: 2013-2016
City: Pas-de-Calais, France
Gross Floor Area (GFA): 742,250 sqm total covered, 52 buildings

Scope of the Mission: Energy Audit (including low-cost and no-cost measures, as well as high-capital-expenditure options for comprehensive renovation).

More Information

Heating Optimization:

  • Reducing operating schedules, start-ups, and shutdowns.
  • Adjusting daytime and nighttime set temperatures.
  • Modifying heating curves.
  • Improving the efficiency of heating production systems, including pumps and regulators.

Facade and Parapet Insulation:

  • Upgrading exterior facade and parapet insulation.
  • Window Replacement:
  • Underfloor and Crawl Space Insulation:
  • Enhancing insulation on the underside of exterior floor slabs and in crawl spaces.

Domestic Hot Water System Optimization:

  • Installing pressure reducers and timers on electric hot water tanks.

Heating Network:

  • Thermal insulation of heating pipelines.
  • Fitting balancing valves and rebalancing networks.
  • Restriction of radiators in certain areas.

Air Renewal Optimization:

  • Implementing AHUs (Air Handling Units) where feasible to optimize air renewal.

Lighting Upgrade:

  • Replacing fixtures with LED luminaires.